depression is wet at 9:00 a.m.
we start drying process
torches complete drying at 11:00
major cracks and voids are filled to seal moisturebelow grade 12:00
surface is trowelled and aggregate is added to surface
\
completed by 6:30 and ready for heavy equipment
by 7:30
This was accomplished by our trained crew within the shutdown window given us. We could have finished in 5 hours if we had not had rain the day before and had to deal with s lot of deep standing water in the cracks and voids.